Fla. Stat. 403.509
Final disposition of application


(1)(a)

If the administrative law judge has granted a request to cancel the certification hearing and has relinquished jurisdiction to the department under the provisions of s. 403.508(6), within 40 days thereafter, the secretary of the department shall act upon the application by written order in accordance with the terms of this act and the stipulation of the parties in requesting cancellation of the certification hearing.If the administrative law judge has not granted a request to cancel the certification hearing under the provisions of s. 403.508(6), within 60 days after receipt of the designated administrative law judge’s recommended order, the board shall act upon the application by written order, approving or denying certification, in accordance with the terms of this act, and stating the reasons for issuance or denial. If certification is denied, the board shall set forth in writing the action the applicant would have to take to secure the board’s approval of the application.

(1)(a)

If the administrative law judge has granted a request to cancel the certification hearing and has relinquished jurisdiction to the department under the provisions of s. 403.508(6), within 40 days thereafter, the secretary of the department shall act upon the application by written order in accordance with the terms of this act and the stipulation of the parties in requesting cancellation of the certification hearing.

(b)

If the administrative law judge has not granted a request to cancel the certification hearing under the provisions of s. 403.508(6), within 60 days after receipt of the designated administrative law judge’s recommended order, the board shall act upon the application by written order, approving or denying certification, in accordance with the terms of this act, and stating the reasons for issuance or denial. If certification is denied, the board shall set forth in writing the action the applicant would have to take to secure the board’s approval of the application.

(2)

The issues that may be raised in any hearing before the board shall be limited to those matters raised in the certification proceeding before the administrative law judge or raised in the recommended order. All parties, or their representatives, or persons who appear before the board shall be subject to the provisions of s. 120.66.

(3)

In determining whether an application should be approved in whole, approved with modifications or conditions, or denied, the board, or secretary when applicable, shall consider whether, and the extent to which, the location, construction, and operation of the electrical power plant will:Provide reasonable assurance that operational safeguards are technically sufficient for the public welfare and protection.Comply with applicable nonprocedural requirements of agencies.Be consistent with applicable local government comprehensive plans and land development regulations.Meet the electrical energy needs of the state in an orderly, reliable, and timely fashion.Effect a reasonable balance between the need for the facility as established pursuant to s. 403.519 and the impacts upon air and water quality, fish and wildlife, water resources, and other natural resources of the state resulting from the construction and operation of the facility.Minimize, through the use of reasonable and available methods, the adverse effects on human health, the environment, and the ecology of the land and its wildlife and the ecology of state waters and their aquatic life.Serve and protect the broad interests of the public.

(a)

Provide reasonable assurance that operational safeguards are technically sufficient for the public welfare and protection.

(b)

Comply with applicable nonprocedural requirements of agencies.

(c)

Be consistent with applicable local government comprehensive plans and land development regulations.

(d)

Meet the electrical energy needs of the state in an orderly, reliable, and timely fashion.

(e)

Effect a reasonable balance between the need for the facility as established pursuant to s. 403.519 and the impacts upon air and water quality, fish and wildlife, water resources, and other natural resources of the state resulting from the construction and operation of the facility.

(f)

Minimize, through the use of reasonable and available methods, the adverse effects on human health, the environment, and the ecology of the land and its wildlife and the ecology of state waters and their aquatic life.

(g)

Serve and protect the broad interests of the public.

(4)(a)

Any transmission line corridor certified by the board, or secretary if applicable, shall meet the criteria of this section. When more than one transmission line corridor is proper for certification under s. 403.503(11) and meets the criteria of this section, the board, or secretary if applicable, shall certify the transmission line corridor that has the least adverse impact regarding the criteria in subsection (3), including costs.If the board, or secretary if applicable, finds that an alternate corridor rejected pursuant to s. 403.5271 as incorporated by reference in s. 403.5064(1)(b) meets the criteria of subsection (3) and has the least adverse impact regarding the criteria in subsection (3), the board, or secretary if applicable, shall deny certification or shall allow the applicant to submit an amended application to include the corridor.If the board, or secretary if applicable, finds that two or more of the corridors that comply with subsection (3) have the least adverse impacts regarding the criteria in subsection (3), including costs, and that the corridors are substantially equal in adverse impacts regarding the criteria in subsection (3), including costs, the board, or secretary if applicable, shall certify the corridor preferred by the applicant if the corridor is one proper for certification under s. 403.503(11).

(4)(a)

Any transmission line corridor certified by the board, or secretary if applicable, shall meet the criteria of this section. When more than one transmission line corridor is proper for certification under s. 403.503(11) and meets the criteria of this section, the board, or secretary if applicable, shall certify the transmission line corridor that has the least adverse impact regarding the criteria in subsection (3), including costs.

(b)

If the board, or secretary if applicable, finds that an alternate corridor rejected pursuant to s. 403.5271 as incorporated by reference in s. 403.5064(1)(b) meets the criteria of subsection (3) and has the least adverse impact regarding the criteria in subsection (3), the board, or secretary if applicable, shall deny certification or shall allow the applicant to submit an amended application to include the corridor.

(c)

If the board, or secretary if applicable, finds that two or more of the corridors that comply with subsection (3) have the least adverse impacts regarding the criteria in subsection (3), including costs, and that the corridors are substantially equal in adverse impacts regarding the criteria in subsection (3), including costs, the board, or secretary if applicable, shall certify the corridor preferred by the applicant if the corridor is one proper for certification under s. 403.503(11).

(5)

The department’s action on a federally required new source review or prevention of significant deterioration permit shall differ from the actions taken by the siting board regarding the certification if the federally approved state implementation plan requires such a different action to be taken by the department. Nothing in this part shall be construed to displace the department’s authority as the final permitting entity under the federally approved permit program. Nothing in this part shall be construed to authorize the issuance of a new source review or prevention of significant deterioration permit which does not conform to the requirements of the federally approved state implementation plan.

(6)

For certifications issued by the board in regard to the properties and works of any agency which is a party to the certification hearing, the board shall have the authority to decide issues relating to the use, the connection thereto, or the crossing thereof, for the electrical power plant and to direct any such agency to execute, within 30 days after the entry of certification, the necessary license or easement for such use, connection, or crossing, subject only to the conditions set forth in such certification. For certifications issued by the department in regard to the properties and works of any agency that is a party to the proceeding, any stipulation filed pursuant to s. 403.508(6)(a) must include a stipulation regarding any issues relating to the use, the connection thereto, or the crossing thereof, for the electrical power plant. Any agency stipulating to the use of, connection to, or crossing of its property must agree to execute, within 30 days after the entry of certification, the necessary license or easement for such use, connection, or crossing, subject only to the conditions set forth in such certification.

(7)

The issuance or denial of the certification by the board or secretary of the department shall be the final administrative action required as to that application.

Source: Section 403.509 — Final disposition of application, https://www.­flsenate.­gov/Laws/Statutes/2024/0403.­509 (accessed Aug. 7, 2025).

403.52
Short title
403.501
Short title
403.502
Legislative intent
403.503
Definitions relating to Florida Electrical Power Plant Siting Act
403.504
Department of Environmental Protection
403.506
Applicability, thresholds, and certification
403.507
Preliminary statements of issues, reports, project analyses, and studies
403.508
Land use and certification hearings, parties, participants
403.509
Final disposition of application
403.510
Superseded laws, regulations, and certification power
403.511
Effect of certification
403.512
Revocation or suspension of certification
403.513
Review
403.514
Enforcement of compliance
403.515
Availability of information
403.516
Modification of certification
403.517
Supplemental applications for sites certified for ultimate site capacity
403.518
Fees
403.519
Exclusive forum for determination of need
403.521
Legislative intent
403.522
Definitions relating to the Florida Electric Transmission Line Siting Act
403.523
Department of Environmental Protection
403.524
Applicability
403.525
Administrative law judge
403.526
Preliminary statements of issues, reports, and project analyses
403.527
Certification hearing, parties, participants
403.528
Alteration of time limits
403.529
Final disposition of application
403.531
Effect of certification
403.532
Revocation or suspension of certification
403.533
Enforcement of compliance
403.536
Superseded laws, regulations, and certification power
403.537
Determination of need for transmission line
403.539
Certification admissible in eminent domain proceedings
403.5055
Application for permits pursuant to s
403.5063
Notice of intent to file application
403.5064
Application
403.5065
Appointment of administrative law judge
403.5066
Determination of completeness
403.5095
Alteration of time limits
403.5112
Filing of notice of certified corridor route
403.5113
Postcertification amendments and review
403.5115
Public notice
403.5116
County and municipal authority unaffected by ch. 75-22
403.5175
Existing electrical power plant site certification
403.5185
Law applicable to applications processed under ss
403.5251
Application
403.5252
Determination of completeness
403.5271
Alternate corridors
403.5272
Informational public meetings
403.5275
Amendment to the application
403.5312
Filing of notice of certified corridor route
403.5315
Modification of certification
403.5317
Postcertification activities
403.5363
Public notices
403.5365
Fees
403.50663
Informational public meetings
403.50665
Land use consistency

Current through Fall 2025

§ 403.509. Final disposition of application's source at flsenate​.gov