Fla. Stat. 403.50665
Land use consistency


(1)

The applicant shall include in the application a statement on the consistency of the site and any associated facilities that constitute a “development,” as defined in s. 380.04, with existing land use plans and zoning ordinances that were in effect on the date the application was filed and a full description of such consistency. This information shall include an identification of those associated facilities that the applicant believes are exempt from the requirements of land use plans and zoning ordinances under the Community Planning Act provisions of chapter 163 and s. 380.04(3).

(2)(a)

Within 45 days after the filing of the application, each local government shall file a determination with the department, the applicant, the administrative law judge, and all parties on the consistency of the site, and any associated facilities that are not exempt from the requirements of land use plans and zoning ordinances under chapter 163 and s. 380.04(3), with existing land use plans and zoning ordinances that were in effect on the date the application was filed, based on the information provided in the application. However, this requirement does not apply to any new electrical generation unit proposed to be constructed and operated on the site of a previously certified electrical power plant or on the site of a power plant that was not previously certified that will be wholly contained within the boundaries of the existing site.The local government may issue its determination up to 55 days later if the application has been determined incomplete based in whole or in part upon a local government request for additional information on land use and zoning consistency as part of the local government’s statement on completeness of the application submitted pursuant to s. 403.5066(1)(a). Incompleteness of information necessary for a local government to evaluate an application may be claimed by the local government as cause for a statement of inconsistency with existing land use plans and zoning ordinances.Notice of the consistency determination shall be published in accordance with the requirements of s. 403.5115.

(2)(a)

Within 45 days after the filing of the application, each local government shall file a determination with the department, the applicant, the administrative law judge, and all parties on the consistency of the site, and any associated facilities that are not exempt from the requirements of land use plans and zoning ordinances under chapter 163 and s. 380.04(3), with existing land use plans and zoning ordinances that were in effect on the date the application was filed, based on the information provided in the application. However, this requirement does not apply to any new electrical generation unit proposed to be constructed and operated on the site of a previously certified electrical power plant or on the site of a power plant that was not previously certified that will be wholly contained within the boundaries of the existing site.

(b)

The local government may issue its determination up to 55 days later if the application has been determined incomplete based in whole or in part upon a local government request for additional information on land use and zoning consistency as part of the local government’s statement on completeness of the application submitted pursuant to s. 403.5066(1)(a). Incompleteness of information necessary for a local government to evaluate an application may be claimed by the local government as cause for a statement of inconsistency with existing land use plans and zoning ordinances.

(c)

Notice of the consistency determination shall be published in accordance with the requirements of s. 403.5115.

(3)(a)

If the local government issues a determination that the proposed site and any nonexempt associated facilities are not consistent or in compliance with local land use plans and zoning ordinances, the applicant may apply to the local government for the necessary local approval to address the inconsistencies identified in the local government’s determination.If the applicant makes such an application to the local government, the time schedules under this act shall be tolled until the local government issues its revised determination on land use and zoning or the applicant otherwise withdraws its application to the local government.If the applicant applies to the local government for necessary local land use or zoning approval, the local government shall commence a proceeding to consider the application for land use or zoning approval within 45 days after receipt of the complete request and shall issue a revised determination within 30 days following the conclusion of that local proceeding. The time schedules and notice requirements under this act shall apply to such revised determination.

(3)(a)

If the local government issues a determination that the proposed site and any nonexempt associated facilities are not consistent or in compliance with local land use plans and zoning ordinances, the applicant may apply to the local government for the necessary local approval to address the inconsistencies identified in the local government’s determination.

(b)

If the applicant makes such an application to the local government, the time schedules under this act shall be tolled until the local government issues its revised determination on land use and zoning or the applicant otherwise withdraws its application to the local government.

(c)

If the applicant applies to the local government for necessary local land use or zoning approval, the local government shall commence a proceeding to consider the application for land use or zoning approval within 45 days after receipt of the complete request and shall issue a revised determination within 30 days following the conclusion of that local proceeding. The time schedules and notice requirements under this act shall apply to such revised determination.

(4)

If any substantially affected person wishes to dispute the local government’s determination, he or she shall file a petition with the designated administrative law judge within 21 days after the publication of notice of the local government’s determination. If a hearing is requested, the provisions of s. 403.508(1) shall apply.

(5)

The dates in this section may be altered upon agreement between the applicant, the local government, and the department pursuant to s. 403.5095.

(6)

If it is determined by the local government that the proposed site or nonexempt associated facility does conform with existing land use plans and zoning ordinances in effect as of the date of the application and no petition has been filed, the responsible zoning or planning authority shall not thereafter change such land use plans or zoning ordinances so as to foreclose construction and operation of the proposed site or directly associated facilities unless certification is subsequently denied or withdrawn.

(7)

The issue of land use and zoning consistency for any proposed alternate intermediate electrical substation which is proposed as part of an alternate electrical transmission line corridor which is accepted by the applicant and the department under s. 403.5271(1)(b) shall be addressed in the supplementary report prepared by the local government on the proposed alternate corridor and shall be considered as an issue at any final certification hearing. If such a proposed alternate intermediate electrical substation is determined not to be consistent with local land use plans and zoning ordinances, then that alternate intermediate electrical substation shall not be certified.

Source: Section 403.50665 — Land use consistency, https://www.­flsenate.­gov/Laws/Statutes/2024/0403.­50665 (accessed Aug. 7, 2025).

403.52
Short title
403.501
Short title
403.502
Legislative intent
403.503
Definitions relating to Florida Electrical Power Plant Siting Act
403.504
Department of Environmental Protection
403.506
Applicability, thresholds, and certification
403.507
Preliminary statements of issues, reports, project analyses, and studies
403.508
Land use and certification hearings, parties, participants
403.509
Final disposition of application
403.510
Superseded laws, regulations, and certification power
403.511
Effect of certification
403.512
Revocation or suspension of certification
403.513
Review
403.514
Enforcement of compliance
403.515
Availability of information
403.516
Modification of certification
403.517
Supplemental applications for sites certified for ultimate site capacity
403.518
Fees
403.519
Exclusive forum for determination of need
403.521
Legislative intent
403.522
Definitions relating to the Florida Electric Transmission Line Siting Act
403.523
Department of Environmental Protection
403.524
Applicability
403.525
Administrative law judge
403.526
Preliminary statements of issues, reports, and project analyses
403.527
Certification hearing, parties, participants
403.528
Alteration of time limits
403.529
Final disposition of application
403.531
Effect of certification
403.532
Revocation or suspension of certification
403.533
Enforcement of compliance
403.536
Superseded laws, regulations, and certification power
403.537
Determination of need for transmission line
403.539
Certification admissible in eminent domain proceedings
403.5055
Application for permits pursuant to s
403.5063
Notice of intent to file application
403.5064
Application
403.5065
Appointment of administrative law judge
403.5066
Determination of completeness
403.5095
Alteration of time limits
403.5112
Filing of notice of certified corridor route
403.5113
Postcertification amendments and review
403.5115
Public notice
403.5116
County and municipal authority unaffected by ch. 75-22
403.5175
Existing electrical power plant site certification
403.5185
Law applicable to applications processed under ss
403.5251
Application
403.5252
Determination of completeness
403.5271
Alternate corridors
403.5272
Informational public meetings
403.5275
Amendment to the application
403.5312
Filing of notice of certified corridor route
403.5315
Modification of certification
403.5317
Postcertification activities
403.5363
Public notices
403.5365
Fees
403.50663
Informational public meetings
403.50665
Land use consistency

Current through Fall 2025

§ 403.50665. Land use consistency's source at flsenate​.gov