Fla. Stat. 403.5064
Application; schedules


(1)

The formal date of filing of a certification application and commencement of the certification review process shall be when the applicant submits:Copies of the certification application in a quantity and format as prescribed by rule to the department and other agencies identified in s. 403.507(2)(a).A statement affirming that the applicant is opting to allow consideration of alternate corridors for an associated transmission line corridor. If alternate corridors are allowed, at the applicant’s option, the portion of the application addressing associated transmission line corridors shall be processed under the schedule set forth in ss. 403.521-403.526, 403.527(4), and 403.5271, including the opportunity for the filing of alternate corridors by third parties; however, if such alternate corridors are filed, the certification hearing shall not be rescheduled as allowed by s. 403.5271(1)(b).The application fee specified under s. 403.518 to the department.

(a)

Copies of the certification application in a quantity and format as prescribed by rule to the department and other agencies identified in s. 403.507(2)(a).

(b)

A statement affirming that the applicant is opting to allow consideration of alternate corridors for an associated transmission line corridor. If alternate corridors are allowed, at the applicant’s option, the portion of the application addressing associated transmission line corridors shall be processed under the schedule set forth in ss. 403.521-403.526, 403.527(4), and 403.5271, including the opportunity for the filing of alternate corridors by third parties; however, if such alternate corridors are filed, the certification hearing shall not be rescheduled as allowed by s. 403.5271(1)(b).

(c)

The application fee specified under s. 403.518 to the department.

(2)

Within 7 days after the filing of an application, the department shall provide to the applicant and the Division of Administrative Hearings the names and addresses of any additional agencies or persons entitled to notice and copies of the application and any amendments. Copies of the application shall be distributed within 5 days by the applicant to these additional agencies. This distribution shall not be a basis for altering the schedule of dates for the certification process.

(3)

Any amendment to the application made prior to certification shall be disposed of as part of the original certification proceeding. Amendment of the application may be considered good cause for alteration of time limits pursuant to s. 403.5095.

(4)

Within 7 days after the filing of an application, the department shall prepare a proposed schedule of dates for determination of completeness, submission of statements of issues, submittal of final reports, and other significant dates to be followed during the certification process, including dates for filing notices of appearance to be a party pursuant to s. 403.508(3). If the application includes one or more associated transmission line corridors, at the request of the applicant filed concurrently with the application, the department shall use the application processing schedule set forth in ss. 403.521-403.526, 403.527(4), and 403.5271 for the associated transmission line corridors, including the opportunity for the filing and review of alternate corridors, if a party proposes alternate transmission line corridor routes for consideration no later than 165 days before the scheduled certification hearing. Notwithstanding an applicant’s option for the transmission line corridor portion of its application to be processed under the proposed schedule, only one certification hearing shall be held for the entire plant in accordance with s. 403.508(2). The proposed schedule shall be timely provided by the department to the applicant, the administrative law judge, all agencies identified pursuant to subsection (2), and all parties. Within 7 days after the filing of the proposed schedule, the administrative law judge shall issue an order establishing a schedule for the matters addressed in the department’s proposed schedule and other appropriate matters, if any.

(5)

Copies of changes and amendments to the application shall be timely distributed by the applicant to all agencies and parties who have received a copy of the application.

(6)

Notice of the filing of the application shall be published in accordance with the requirements of s. 403.5115.

Source: Section 403.5064 — Application; schedules, https://www.­flsenate.­gov/Laws/Statutes/2024/0403.­5064 (accessed Aug. 7, 2025).

403.52
Short title
403.501
Short title
403.502
Legislative intent
403.503
Definitions relating to Florida Electrical Power Plant Siting Act
403.504
Department of Environmental Protection
403.506
Applicability, thresholds, and certification
403.507
Preliminary statements of issues, reports, project analyses, and studies
403.508
Land use and certification hearings, parties, participants
403.509
Final disposition of application
403.510
Superseded laws, regulations, and certification power
403.511
Effect of certification
403.512
Revocation or suspension of certification
403.513
Review
403.514
Enforcement of compliance
403.515
Availability of information
403.516
Modification of certification
403.517
Supplemental applications for sites certified for ultimate site capacity
403.518
Fees
403.519
Exclusive forum for determination of need
403.521
Legislative intent
403.522
Definitions relating to the Florida Electric Transmission Line Siting Act
403.523
Department of Environmental Protection
403.524
Applicability
403.525
Administrative law judge
403.526
Preliminary statements of issues, reports, and project analyses
403.527
Certification hearing, parties, participants
403.528
Alteration of time limits
403.529
Final disposition of application
403.531
Effect of certification
403.532
Revocation or suspension of certification
403.533
Enforcement of compliance
403.536
Superseded laws, regulations, and certification power
403.537
Determination of need for transmission line
403.539
Certification admissible in eminent domain proceedings
403.5055
Application for permits pursuant to s
403.5063
Notice of intent to file application
403.5064
Application
403.5065
Appointment of administrative law judge
403.5066
Determination of completeness
403.5095
Alteration of time limits
403.5112
Filing of notice of certified corridor route
403.5113
Postcertification amendments and review
403.5115
Public notice
403.5116
County and municipal authority unaffected by ch. 75-22
403.5175
Existing electrical power plant site certification
403.5185
Law applicable to applications processed under ss
403.5251
Application
403.5252
Determination of completeness
403.5271
Alternate corridors
403.5272
Informational public meetings
403.5275
Amendment to the application
403.5312
Filing of notice of certified corridor route
403.5315
Modification of certification
403.5317
Postcertification activities
403.5363
Public notices
403.5365
Fees
403.50663
Informational public meetings
403.50665
Land use consistency

Current through Fall 2025

§ 403.5064. Application; schedules's source at flsenate​.gov