Fla. Stat. 373.423
Inspection


(1)

During the construction or alteration of any stormwater management system, dam, impoundment, reservoir, appurtenant work, or works, the governing board or department pursuant to s. 403.091 shall make at its expense such periodic inspections as it deems necessary to ensure conformity with the approved plans and specifications included in the permit.

(2)

If during construction or alteration the governing board or department finds that the work is not being done in accordance with the approved plans and specifications as indicated in the permit, it shall give the permittee written notice stating with which particulars of the approved plans and specifications the construction is not in compliance and shall order immediate compliance with such plans and specifications. The failure to act in accordance with the orders of the governing board or department after receipt of written notice shall result in the initiation of revocation proceedings in accordance with s. 373.429.

(3)

Upon completion of the work, the executive director of the district or the Department of Environmental Protection or its successor agency shall have periodic inspections made of permitted stormwater management systems, dams, reservoirs, impoundments, appurtenant work, or works to protect the public health and safety and the natural resources of the state. No person shall refuse immediate entry or access to any authorized representative of the governing board or the department who requests entry for purposes of such inspection and presents appropriate credentials.

Source: Section 373.423 — Inspection, https://www.­flsenate.­gov/Laws/Statutes/2024/0373.­423 (accessed Aug. 7, 2025).

373.403
Definitions
373.406
Exemptions
373.407
Determination of qualification for an agricultural-related exemption
373.409
Headgates, valves, and measuring devices
373.413
Permits for construction or alteration
373.414
Additional criteria for activities in surface waters and wetlands
373.415
Protection zones
373.416
Permits for maintenance or operation
373.417
Citation of rule
373.418
Rulemaking
373.419
Completion report
373.421
Delineation methods
373.422
Applications for activities on state sovereignty lands or other state lands
373.423
Inspection
373.426
Abandonment
373.427
Concurrent permit review
373.428
Federal consistency
373.429
Revocation and modification of permits
373.430
Prohibitions, violation, penalty, intent
373.433
Abatement
373.436
Remedial measures
373.439
Emergency measures
373.441
Role of counties, municipalities, and local pollution control programs in permit processing
373.443
Immunity from liability
373.451
Short title
373.453
Surface water improvement and management plans and programs
373.459
Funds for surface water improvement and management
373.461
Lake Apopka improvement and management
373.462
Legislative findings and intent
373.463
Heartland headwaters annual report
373.468
The Harris Chain of Lakes restoration program
373.469
Indian River Lagoon Protection Program
373.4131
Statewide environmental resource permitting rules
373.4132
Dry storage facility permitting
373.4133
Port conceptual permits
373.4134
Water quality enhancement areas
373.4135
Mitigation banks and offsite regional mitigation
373.4136
Establishment and operation of mitigation banks
373.4137
Mitigation requirements for specified transportation projects
373.4138
High Speed Rail Project
373.4139
Local government transportation infrastructure mitigation requirements
373.4141
Permits
373.4142
Water quality within stormwater treatment systems
373.4143
Declaration of policy
373.4144
Federal environmental permitting
373.4145
Part IV permitting program within the geographical jurisdiction of the Northwest Florida Water Management District
373.4146
State assumption of the federal Clean Water Act, section 404 dredge and fill permitting program
373.4149
Miami-Dade County Lake Belt Plan
373.4185
List of flocculants permitted
373.4211
Ratification of chapter 17-340, Florida Administrative Code, on the delineation of the landward extent of wetlands and surface waters
373.4271
Conduct of challenge to consolidated environmental resource permit or associated variance or sovereign submerged lands authorization issued in connection with deepwater ports
373.4275
Review of consolidated orders
373.4415
Role of Miami-Dade County in processing permits for limerock mining in Miami-Dade County Lake Belt
373.4591
Improvements on private agricultural lands
373.4592
Everglades improvement and management
373.4593
Florida Bay Restoration
373.4595
Northern Everglades and Estuaries Protection Program
373.4596
State compliance with stormwater management programs
373.4597
The Geneva Freshwater Lens Protection Act
373.4598
Water storage reservoirs
373.4599
Water storage north of Lake Okeechobee
373.41365
Adoption and modification of rules to ensure financial assurances for long-term management of mitigation under ss
373.41492
Miami-Dade County Lake Belt Mitigation Plan
373.41495
Lake Belt Mitigation Trust Fund
373.45922
South Florida Water Management District
373.45924
South Florida Water Management District
373.45926
Everglades Trust Fund
373.45931
Alligator Alley tolls

Current through Fall 2025

§ 373.423. Inspection's source at flsenate​.gov