Fla. Stat. 163.3208
Substation approval process


(1)

It is the intent of the Legislature to maintain, encourage, and ensure adequate and reliable electric infrastructure in the state. It is essential that electric infrastructure be constructed and maintained in various locations in order to ensure the efficient and reliable delivery of electric service. Electric infrastructure should be constructed, to the maximum extent practicable, to achieve compatibility with adjacent and surrounding land uses, and the criteria included in this section are intended to balance the need for electricity with land use compatibility.

(2)

The term “electric substation” means an electric substation, including accessory administration or maintenance buildings and related accessory uses and structures, which takes electricity from the transmission grid and converts it to another voltage or lower voltage so it can be distributed to customers through one or more lines.

(3)

Electric substations are a critical component of electric transmission and distribution. Except for substations in s. 163.3205(2)(c), local governments may adopt and enforce reasonable land development regulations for new and existing electric substations, addressing only setback, landscaping, buffering, screening, lighting, and other aesthetic compatibility-based standards. Vegetated buffers or screening beneath aerial access points to the substation equipment shall not be required to have a mature height in excess of 14 feet.

(4)

New and existing electric substations shall be a permitted use in all land use categories in the applicable local government comprehensive plan and zoning districts within a utility’s service territory except those designated as preservation, conservation, or historic preservation on the future land use map or duly adopted ordinance. If a local government has not adopted reasonable standards for substation siting in accordance with subsection (3), the following standards shall apply to new electric substations:In nonresidential areas, the substation must comply with the setback and landscaped buffer area criteria applicable to other similar uses in that district, if any.Unless the local government approves a lesser setback or landscape requirement, in residential areas, a setback of up to 100 feet between the substation property boundary and permanent equipment structures shall be maintained as follows:
For setbacks between 100 feet and 50 feet, an open green space shall be formed by installing native landscaping, including trees and shrub material, consistent with the relevant local government’s land development regulations. Substation equipment shall be protected by a security fence consistent with the relevant local government’s land development regulations.
For setbacks of less than 50 feet, a buffer wall 8 feet high or a fence 8 feet high with native landscaping consistent with the relevant local government’s regulations shall be installed around the substation.

(a)

In nonresidential areas, the substation must comply with the setback and landscaped buffer area criteria applicable to other similar uses in that district, if any.

(b)

Unless the local government approves a lesser setback or landscape requirement, in residential areas, a setback of up to 100 feet between the substation property boundary and permanent equipment structures shall be maintained as follows:For setbacks between 100 feet and 50 feet, an open green space shall be formed by installing native landscaping, including trees and shrub material, consistent with the relevant local government’s land development regulations. Substation equipment shall be protected by a security fence consistent with the relevant local government’s land development regulations.For setbacks of less than 50 feet, a buffer wall 8 feet high or a fence 8 feet high with native landscaping consistent with the relevant local government’s regulations shall be installed around the substation.
1. For setbacks between 100 feet and 50 feet, an open green space shall be formed by installing native landscaping, including trees and shrub material, consistent with the relevant local government’s land development regulations. Substation equipment shall be protected by a security fence consistent with the relevant local government’s land development regulations.
2. For setbacks of less than 50 feet, a buffer wall 8 feet high or a fence 8 feet high with native landscaping consistent with the relevant local government’s regulations shall be installed around the substation.

(5)

If the application for a proposed electric substation or for changes to an existing electric substation demonstrates that the substation design is consistent with the local government’s applicable setback, landscaping, buffering, screening, and other aesthetic compatibility-based standards, the application for development approval for or changes to the substation shall be approved.

(6)(a)

This paragraph applies to the proposed placement or construction of a new electric substation within a residential area. Before submitting an application for the location of a new electric substation in residential areas, the utility shall consult with the local government regarding the selection of a site. The utility shall provide information regarding the utility’s preferred site and as many as three alternative available sites, including sites within nonresidential areas, that are technically and electrically reasonable for the load to be served, if the local government deems that the siting of a new electric substation warrants this additional review and consideration. The final determination on the site application as to the preferred and alternative sites shall be made solely by the local government within 90 days of presentation of all the necessary and required information on the preferred site and on the alternative sites. In the event the utility and the local government are unable to reach agreement on an appropriate location, the substation site selection shall be submitted to mediation conducted pursuant to ss. 44.401-44.406, unless otherwise agreed to in writing by the parties, and the mediation shall be concluded within 30 days unless extended by written agreement of the parties. The 90-day time period for the local government to render a final decision on the site application is tolled from the date a notice of intent to mediate the site selection issue is served on the utility or local government, until the mediation is concluded, terminated, or an impasse is declared. The local government and utility may agree to waive or extend this 90-day time period. Upon rendition of a final decision of the local government, a person may pursue available legal remedies in accordance with law, and the matter shall be considered on an expedited basis.A local government’s land development and construction regulations for new electric substations or for changes to existing electric substations and the local government’s review of an application for the placement or construction of a new electric substation or for changes to an existing electric substation shall only address land development, zoning, or aesthetic compatibility-based issues. In such local government regulations or review, a local government may not require information or evaluate a utility’s business decisions about its service, customer demand for its service, or quality of its service to or from a particular area or site, unless the utility voluntarily offers this information to the local government.

(6)(a)

This paragraph applies to the proposed placement or construction of a new electric substation within a residential area. Before submitting an application for the location of a new electric substation in residential areas, the utility shall consult with the local government regarding the selection of a site. The utility shall provide information regarding the utility’s preferred site and as many as three alternative available sites, including sites within nonresidential areas, that are technically and electrically reasonable for the load to be served, if the local government deems that the siting of a new electric substation warrants this additional review and consideration. The final determination on the site application as to the preferred and alternative sites shall be made solely by the local government within 90 days of presentation of all the necessary and required information on the preferred site and on the alternative sites. In the event the utility and the local government are unable to reach agreement on an appropriate location, the substation site selection shall be submitted to mediation conducted pursuant to ss. 44.401-44.406, unless otherwise agreed to in writing by the parties, and the mediation shall be concluded within 30 days unless extended by written agreement of the parties. The 90-day time period for the local government to render a final decision on the site application is tolled from the date a notice of intent to mediate the site selection issue is served on the utility or local government, until the mediation is concluded, terminated, or an impasse is declared. The local government and utility may agree to waive or extend this 90-day time period. Upon rendition of a final decision of the local government, a person may pursue available legal remedies in accordance with law, and the matter shall be considered on an expedited basis.

(b)

A local government’s land development and construction regulations for new electric substations or for changes to existing electric substations and the local government’s review of an application for the placement or construction of a new electric substation or for changes to an existing electric substation shall only address land development, zoning, or aesthetic compatibility-based issues. In such local government regulations or review, a local government may not require information or evaluate a utility’s business decisions about its service, customer demand for its service, or quality of its service to or from a particular area or site, unless the utility voluntarily offers this information to the local government.

(7)

Substation siting standards adopted after the effective date of this act do not apply to applications for new electric substations or for changes to existing electric substations which were submitted before the notice of the local government’s adoption hearing.

(8)(a)

If a local government has adopted standards for the siting of new electric substations or for changes to existing electric substations within any of the local government’s land use categories or zoning districts, the local government shall grant or deny a properly completed application for a permit to locate a new electric substation or change an existing electric substation within the land use category or zoning district within 90 days after the date the properly completed application is declared complete in accordance with the applicable local government application procedures. If the local government fails to approve or deny a properly completed application for a new electric substation or for changes to an existing electric substation within the timeframes set forth, the application is automatically approved, and the applicant may proceed with construction consistent with its application without interference or penalty. Issuance of such local permit does not relieve the applicant from complying with applicable federal or state laws or regulations and other applicable local land development or building regulations, if any.The local government shall notify the permit applicant within 30 days after the date the application is submitted as to whether the application is, for administrative purposes only, properly completed and has been properly submitted. Further completeness determinations shall be provided within 15 days after the receipt of additional information. However, such determination is not approval of the application.To be effective, a waiver of the timeframes set forth in this subsection must be voluntarily agreed to by the utility applicant and the local government. A local government may request, but not require, a waiver of the timeframes by the applicant, except that, with respect to a specific application, a one-time waiver may be required in the case of a declared local, state, or federal emergency that directly affects the administration of all permitting activities of the local government.The local government may establish reasonable timeframes within which the required information to cure the application deficiency is to be provided, or the application will be considered withdrawn or closed.

(8)(a)

If a local government has adopted standards for the siting of new electric substations or for changes to existing electric substations within any of the local government’s land use categories or zoning districts, the local government shall grant or deny a properly completed application for a permit to locate a new electric substation or change an existing electric substation within the land use category or zoning district within 90 days after the date the properly completed application is declared complete in accordance with the applicable local government application procedures. If the local government fails to approve or deny a properly completed application for a new electric substation or for changes to an existing electric substation within the timeframes set forth, the application is automatically approved, and the applicant may proceed with construction consistent with its application without interference or penalty. Issuance of such local permit does not relieve the applicant from complying with applicable federal or state laws or regulations and other applicable local land development or building regulations, if any.

(b)

The local government shall notify the permit applicant within 30 days after the date the application is submitted as to whether the application is, for administrative purposes only, properly completed and has been properly submitted. Further completeness determinations shall be provided within 15 days after the receipt of additional information. However, such determination is not approval of the application.

(c)

To be effective, a waiver of the timeframes set forth in this subsection must be voluntarily agreed to by the utility applicant and the local government. A local government may request, but not require, a waiver of the timeframes by the applicant, except that, with respect to a specific application, a one-time waiver may be required in the case of a declared local, state, or federal emergency that directly affects the administration of all permitting activities of the local government.

(d)

The local government may establish reasonable timeframes within which the required information to cure the application deficiency is to be provided, or the application will be considered withdrawn or closed.

Source: Section 163.3208 — Substation approval process, https://www.­flsenate.­gov/Laws/Statutes/2024/0163.­3208 (accessed Aug. 7, 2025).

163.325
Short title
163.2511
Urban infill and redevelopment
163.2514
Growth Policy Act
163.2517
Designation of urban infill and redevelopment area
163.2520
Economic incentives
163.3161
Short title
163.3162
Agricultural lands and practices
163.3163
Applications for development permits
163.3164
Community Planning Act
163.3167
Scope of act
163.3168
Planning innovations and technical assistance
163.3171
Areas of authority under this act
163.3174
Local planning agency
163.3175
Legislative findings on compatibility of development with military installations
163.3177
Required and optional elements of comprehensive plan
163.3178
Coastal management
163.3179
Family homestead
163.3180
Concurrency
163.3181
Public participation in the comprehensive planning process
163.3182
Transportation deficiencies
163.3184
Process for adoption of comprehensive plan or plan amendment
163.3187
Process for adoption of small scale comprehensive plan amendment
163.3191
Evaluation and appraisal of comprehensive plan
163.3194
Legal status of comprehensive plan
163.3197
Legal status of prior comprehensive plan
163.3201
Relationship of comprehensive plan to exercise of land development regulatory authority
163.3202
Land development regulations
163.3204
Cooperation by state and regional agencies
163.3205
Solar facility approval process
163.3206
Fuel terminals
163.3208
Substation approval process
163.3209
Electric transmission and distribution line right-of-way maintenance
163.3210
Natural gas resiliency and reliability infrastructure
163.3211
Conflict with other statutes
163.3213
Administrative review of land development regulations
163.3215
Standing to enforce local comprehensive plans through development orders
163.3217
Municipal overlay for municipal incorporation
163.3220
Short title
163.3221
Florida Local Government Development Agreement Act
163.3223
Applicability
163.3225
Public hearings
163.3227
Requirements of a development agreement
163.3229
Duration of a development agreement and relationship to local comprehensive plan
163.3231
Consistency with the comprehensive plan and land development regulations
163.3233
Local laws and policies governing a development agreement
163.3235
Periodic review of a development agreement
163.3237
Amendment or cancellation of a development agreement
163.3239
Recording and effectiveness of a development agreement
163.3241
Modification or revocation of a development agreement to comply with subsequently enacted state and federal law
163.3243
Enforcement
163.3245
Sector plans
163.3246
Local government comprehensive planning certification program
163.3248
Rural land stewardship areas
163.3251
Definitions
163.3252
Local manufacturing development program
163.3253
Coordinated manufacturing development approval process
163.31771
Accessory dwelling units
163.31777
Public schools interlocal agreement
163.31801
Impact fees
163.31802
Prohibited standards for security devices
163.32051
Floating solar facilities
163.32466
Readoption by ordinance of plan amendments adopted pursuant to former s

Current through Fall 2025

§ 163.3208. Substation approval process's source at flsenate​.gov