Fla. Stat. 337.141
Payment of construction or maintenance contracts


(1)

As used in this section, the terms “dispute” or “pending claim” refer to a dispute or pending claim between the prime contractor and the department.

(2)

Each contract for construction or maintenance entered into pursuant to this chapter shall provide for final payment within 75 days of final field acceptance, provided all documents which are required by the contract from the contractor, with the exception of the acceptance letter and a consent by the contractor’s surety for release of payment of the retained percentage and final estimate to the contractor, are received within 30 days of final field acceptance. If the contractor fails to provide the documents within 30 days after final field acceptance, payment shall be made within 45 days of receipt by the department of such documents. The department shall notify the contractor within 20 days of receipt of the documents which are required for payment if such documents are incomplete and shall specifically list for the contractor which documents have not been submitted. Should the department fail to notify the contractor within 20 days, regardless of completeness of the documents, the time required for payment shall begin. The period of time from the offer of final payment to the receipt by the department of the acceptance letter and surety’s consent shall not count as part of the 75-day or 45-day time periods. Final payment shall not be so made as to any amount which is in dispute or the subject of a pending claim, but shall be so made as to that portion of a contract or those amounts which are not in dispute or the subject of a pending claim. However, such partial payment shall not constitute any bar, admission, or estoppel or have any other effect as to those payments that are in dispute or the subject of a pending claim. No payment may be made to a construction or maintenance contractor until the department has on file proof, in the form of a notarized affidavit from the contractor, that all motor vehicles that he or she operates in this state are registered in compliance with chapter 320.

(3)

For each day after 75 days, or 30 days after settlement of a claim, the department shall pay to the contractor interest at the rate set forth in s. 55.03.

(4)

If a contractor fails to submit all documents required for final payment within 2 years after final acceptance of the work or within 1 year after the offer by the department of final payment, whichever occurs later, any amount owed as final payment shall be considered to be forfeited. The forfeiture will not apply to documents that are the subject of existing claims or pending legal proceedings. Written notice shall be given by the department at least 60 days prior to forfeiture.

Source: Section 337.141 — Payment of construction or maintenance contracts, https://www.­flsenate.­gov/Laws/Statutes/2024/0337.­141 (accessed Aug. 7, 2025).

337.02
Purchases by department subject to competitive bids
337.03
Authority of department to purchase surplus properties from the Federal Government
337.11
Contracting authority of department
337.14
Application for qualification
337.015
Administration of public contracts
337.16
Disqualification of delinquent contractors from bidding
337.17
Bid guaranty
337.18
Surety bonds for construction or maintenance contracts
337.19
Suits by and against department
337.023
Sale of building
337.25
Acquisition, lease, and disposal of real and personal property
337.025
Innovative transportation projects
337.26
Execution and effect of instruments of sale, lease, or conveyance executed by department
337.026
Authority of department to enter into agreements for construction aggregate materials
337.27
Exercise of power of eminent domain by department
337.027
Authority to implement a business development program
337.29
Vesting of title to roads
337.105
Qualifications of professional consultants and other providers of contractual services
337.106
Professional service providers
337.107
Contracts for right-of-way services
337.108
Hazardous materials and pollutants
337.111
Contracting for monuments and memorials to military veterans at rest areas
337.125
Socially and economically disadvantaged business enterprises
337.135
Socially and economically disadvantaged business enterprises
337.139
Efforts to encourage awarding contracts to disadvantaged business enterprises
337.141
Payment of construction or maintenance contracts
337.145
Offsetting payments
337.162
Professional services
337.164
Legislative intent with respect to integrity of public contracting process
337.165
Contract crime
337.166
Moneys recovered for violations of antitrust laws
337.167
Administrative procedures
337.168
Confidentiality of official estimates and bid analysis and monitoring system
337.169
Effect of ch. 83-4 on existing remedies
337.175
Retainage
337.185
State Arbitration Board
337.195
Limits on liability
337.221
Claims settlement process
337.242
Acquisition of rail corridors
337.243
Notification of land use changes in designated transportation corridors
337.251
Lease of property for joint public-private development and areas above or below department property
337.0261
Construction aggregate materials
337.0262
Purchase and use of clay, peat, gravel, sand, or any other solid substance extracted from borrow pits
337.273
Transportation corridors
337.274
Authority of department agent or employee to enter lands, waters, and premises of another in the performance of duties
337.276
Issuance of bonds for right-of-way land acquisition and state bridge construction
337.401
Use of right-of-way for utilities subject to regulation
337.402
Damage to public road caused by utility
337.403
Interference caused by utility
337.404
Removal or relocation of utility facilities
337.405
Trees or other vegetation within rights-of-way of State Highway System or publicly owned rail corridors
337.406
Unlawful use of state transportation facility right-of-way
337.407
Regulation of signs and lights within rights-of-way
337.408
Regulation of bus stops, benches, transit shelters, street light poles, waste disposal receptacles, and modular news racks within rights-of-way
337.409
Willfully or maliciously removing, damaging, destroying, altering, or appropriating benches, transit shelters, waste receptacles, or advertising displayed thereon
337.1075
Contracts for planning services
337.1101
Contracting and procurement authority of the department
337.2505
Donations for landscape projects
337.02611
Phosphogypsum as a construction aggregate material
337.2735
Recording of municipal maps of reservation for transportation corridors and transportation facilities
337.4061
Definitions

Current through Fall 2025

§ 337.141. Payment of construction or maintenance contracts's source at flsenate​.gov