Fla. Stat. 161.055
Concurrent processing of permits


(1)

When an activity for which a permit is required under this chapter also requires a permit, authorization, or approval described in paragraph (2)(b), including a port conceptual permit pursuant to s. 373.4133, the department may, by rule, provide that the activity may be undertaken only upon receipt of a single permit from the department called a “joint coastal permit,” as provided in this section.

(2)

The department may adopt rules requiring concurrent application submittal and establishing a concurrent review and permitting procedure for any activity regulated under this chapter that also requires one or more of the permits, authorizations, or approvals described in paragraph (a) or paragraph (b). The rules must establish concurrent procedures for processing applications under this part with one or more of the permits, authorizations, or approvals described in paragraph (a) or paragraph (b). An applicant that proposes such an activity must submit, as part of the permit application under this chapter, all information necessary to satisfy the requirements for issuance of any required:Proprietary authorization under chapters 253 and 258 to use submerged lands owned by the Board of Trustees of the Internal Improvement Trust Fund; andEnvironmental resource permit or dredge and fill permit under part IV of chapter 373.

The timeframes for license approval or denial set forth in s. 120.60(1) do not commence until all required information is received. The rules authorized under this section may also require submittal of such information as is necessary to determine whether the proposed activity will occur on submerged lands owned by the Board of Trustees of the Internal Improvement Trust Fund, and shall contain provisions for permit processing and issuance of orders which are consistent with s. 373.427 and provisions for providing notice of applications which are consistent with s. 373.413. Authorization under this subsection may not be issued unless the requirements for issuance of any additional required authorizations, permits, waivers, variances, and approvals described in paragraph (a) or paragraph (b) are also satisfied.

(a)

Proprietary authorization under chapters 253 and 258 to use submerged lands owned by the Board of Trustees of the Internal Improvement Trust Fund; and

(b)

Environmental resource permit or dredge and fill permit under part IV of chapter 373.

(3)

The review of agency action on an application for issuance of a joint coastal permit must be as provided in s. 373.4275.

Source: Section 161.055 — Concurrent processing of permits, https://www.­flsenate.­gov/Laws/Statutes/2024/0161.­055 (accessed Aug. 7, 2025).

161.011
Short title
161.021
Definitions
161.031
Personnel and facilities
161.041
Permits required
161.042
Coastal construction and excavation in barrier beach inlets
161.051
Coastal construction by persons, firms, corporations, or local authorities
161.052
Coastal construction and excavation
161.053
Coastal construction and excavation
161.054
Administrative fines
161.055
Concurrent processing of permits
161.061
Coastal construction serving no public purpose, endangering human life, health, or welfare, or becoming unnecessary or undesirable
161.071
Prosecuting officers to assist enforcement of this part
161.081
Powers of Department of Legal Affairs
161.082
Review of innovative technologies for beach nourishment
161.085
Rigid coastal armoring structures
161.088
Declaration of public policy respecting beach erosion control and beach restoration and nourishment projects
161.091
Beach management
161.101
State and local participation in authorized projects and studies relating to beach management and erosion control
161.111
Shore erosion emergency
161.121
Penalty
161.131
Construction of ss
161.141
Property rights of state and private upland owners in beach restoration project areas
161.142
Declaration of public policy relating to improved navigation inlets
161.143
Inlet management
161.144
Policy guidance related to sand source management
161.151
Definitions
161.161
Procedure for approval of projects
161.163
Coastal areas used by sea turtles
161.181
Recording of resolution and survey of board of trustees
161.191
Vesting of title to lands
161.201
Preservation of common-law rights
161.211
Cancellation of resolution for nonperformance by board of trustees
161.212
Judicial review relating to permits and licenses
161.242
Harvesting of sea oats and sea grapes prohibited
161.0415
Citation of rule
161.0531
Development agreements
161.0535
Permits

Current through Fall 2025